Operations Management

Complete Formula Sheet · 12 topic areas

Capacity Planning

Capacity

Capacity = (Maximum production rate per hour) × (Number of hours worked per period)
Design capacity = maximum designed output rate. Theoretical capacity = achievable only under ideal conditions, short-term. Effective/utilised capacity is always ≤ design capacity due to real-world losses (breakdowns, changeovers, absenteeism).
◆ ◆ ◆
Location Analysis

Factor Rating & Location Break-Even

Weighted Factor-Rating Method

Composite Score (per location) = Σ (Rating × Weight)Sum the weighted scores across all factors — highest composite score wins

Locational Break-Even / Cost-Volume Analysis

Total Cost (at a location) = Fixed Cost + (Variable Cost per unit × Volume)Plot for each candidate location; the crossover point is where two locations' total costs are equal
◆ ◆ ◆
Make-or-Buy

Make-or-Buy Decision

BasisFormula
Cost of BuyingPrice per unit × Demand
Cost of MakingFixed Cost + (Variable Cost per unit × Demand)
Rule Choose whichever option gives the lower total cost — but flag a decision as marginal if the gap is small, since a small shift in demand/cost can flip it.
◆ ◆ ◆
Forecasting

Forecasting Methods

Simple Moving Average = (Sum of demand in last n periods) / n
Weighted Moving Average = Σ (Weighti × Demandi)weights assigned to recent periods sum to 1, with more weight on recent data
Exponential Smoothing: Ft = Ft-1 + α (At-1 − Ft-1)F = forecast, A = actual, α = smoothing constant (0–1)
◆ ◆ ◆
Break-Even Analysis

Break-Even Point (BEP)

BEP (units) = Fixed Cost / (Selling Price per unit − Variable Cost per unit)
BEP (₹ sales value) = Fixed Cost / Contribution Margin Ratio (CMR)
Note The denominator (Price − Variable Cost) is called the Contribution per unit — see Product-Mix section for CMR.
◆ ◆ ◆
Product-Mix / Contribution

Contribution Margin & Profit

CMR (per product) = (Price − Variable Cost) / Price
Weighted-Average CMR = Σ (CMRi × % of sales-mixi)
Total Contribution = Total Sales × Weighted-Average CMR
Profit = Total Contribution − Fixed Cost
◆ ◆ ◆
Inventory / EOQ

Reorder Point & Economic Order Quantity

Reorder Point (ROP) = Lead Time Demand + Safety Stock
EOQ: Q* = √(2DS / H)D = annual demand · S = ordering cost per order · H = carrying cost per unit per year
Number of Orders per Year = D / EOQ
Order Cycle Time = (Days per year) / (Number of orders per year)
Trade-off Ordering cost ↓ and Carrying cost ↑ as order size rises — EOQ is the quantity where total cost (ordering + carrying) is minimised.
◆ ◆ ◆
Vendor Rating

Quality-Delivery-Price (QDP) Method

Quality Score = (Qty Accepted / Qty Supplied) × Weight for Quality
Delivery Score = (Qty Received on time / Qty Ordered as per PO) × Weight for Delivery
Price Score = (Lowest Quoted Price / Vendor's Quoted Price) × Weight for Price
Composite Score = Quality Score + Delivery Score + Price ScoreHighest composite score wins the vendor selection
◆ ◆ ◆
Work / Time Study

Normal Time & Standard Time

Normal Time (NT) = Observed Time (OT) × Rating Factor (RF) / 100For a full job: NT = Σ (OT × RF) across all elements
Standard Time (ST) = Normal Time × (1 + Allowance %)equivalently: ST = NT + Allowances
Allowances Personal · Fatigue · Delay · Contingency · Interference · Policy — added on top of Normal Time to reach Standard Time.
◆ ◆ ◆
Sequencing

Mean Flow Time & Critical Ratio

Mean Flow Time = Total (cumulative) Flow Time / Number of Jobs
Critical Ratio (CR) = (Time remaining until due date) / (Work time remaining)CR < 1 → job is behind schedule and needs priority
Rule SPT (Shortest Processing Time first) mathematically minimises Mean Flow Time. EDD (Earliest Due Date first) minimises maximum lateness.
◆ ◆ ◆
Replacement Analysis

Average Annual Cost Method

Total Cost (Year n) = Cumulative Maintenance Cost + Depreciation(no resale value case)
Total Cost (Year n) = (Purchase Price + Cumulative Maintenance) − Resale Value(with declining resale value)
Average Cost per Year = Total Cost (Year n) / n
Rule Replace the asset at the year where Average Cost per Year is at its minimum — the year just before it starts rising again.
◆ ◆ ◆
SQC / Control Charts

C-Chart & p-Chart

C-Chart (defects per unit)

c̄ (Centre Line) = Total defects / Number of samples
UCL = c̄ + 3√c̄  |  LCL = c̄ − 3√c̄ (LCL taken as 0 if negative)

p-Chart (fraction defective)

p̄ (Centre Line) = Total defectives / (Number of lots × lot size)
UCL = p̄ + 3√[p̄(1−p̄)/n]  |  LCL = p̄ − 3√[p̄(1−p̄)/n]
Rule All ±3 limits assume Normal distribution; a point outside UCL/LCL signals an assignable (special) cause needing investigation.